出版物
International arbitration report
In this edition, we focused on the Shanghai International Economic and Trade Arbitration Commission’s (SHIAC) new arbitration rules, which take effect January 1, 2024.
Singapore | 出版物 | October 2024
Reproduced from Practical Law with the permission of the publishers. For further information visit www.practicallaw.com.
In Vietnam Oil and Gas Group v Joint Stock Company (Power Machines – ZTL, LMZ, Electrolisa Energomachexport) [2024] SHGH 2024, the Singapore High Court made the rare finding that an arbitral award was issued in breach of natural justice. It remitted the award to the Tribunal for further consideration, rather than setting it aside.
The Singapore High Court has remitted an arbitral award to the tribunal because it breached the principles of natural justice.
The dispute arose from the construction of a power plant for Vietnam Oil and Gas Group (PVN). The project was disrupted when a member of the respondents' consortium, Power Machines (PM), was placed on the United States sanctions list, causing subcontractors to stop work.
PM purported to terminate the contract (First Termination Notice), stating that the sanctions constituted force majeure. PM then issued a second termination notice (Second Termination Notice) because PVN allegedly defaulted in making outstanding payments. PVN contested PM's right to terminate and the dispute was referred to arbitration in Singapore under the SIAC Arbitration Rules.
In its final award, the tribunal decided that the First Termination Notice was defective because the sanctions did not constitute force majeure but that the Second Termination Notice was effective.
PM obtained leave to enforce the award in Singapore, which PVN then applied to set aside. It argued that the award breached the rules of natural justice because the decision on the validity of the Second Termination Notice was based on arguments that the parties did not raise and did not have the chance to respond to.
The Singapore High Court agreed that the award was made in breach of natural justice. However, it decided to remit the award to the tribunal, rather than set aside the award. It did so on the basis that:
The decision is significant as it demonstrates the utility of the power to remit awards, rather than set them aside, in appropriate cases. It is also a reminder to parties looking to bring tactical challenges that even where natural justice concerns are upheld, they may not necessarily result in an award being set aside. At the same time, it is also another reminder to arbitrators that arguments must be in play if they are to form any part of the reasoning in an award.
The Singapore High Court has remitted an arbitral award to the tribunal because it breached the principles of natural justice.
The dispute arose from the construction of a power plant for Vietnam Oil and Gas Group (PVN). The project was disrupted when a member of the respondents' consortium, Power Machines (PM), was placed on the United States sanctions list, causing subcontractors to stop work.
PM purported to terminate the contract (First Termination Notice), stating that the sanctions constituted force majeure. PM then issued a second termination notice (Second Termination Notice) because PVN allegedly defaulted in making outstanding payments. PVN contested PM's right to terminate and the dispute was referred to arbitration in Singapore under the SIAC Arbitration Rules.
In its final award, the tribunal decided that the First Termination Notice was defective because the sanctions did not constitute force majeure but that the Second Termination Notice was effective.
PM obtained leave to enforce the award in Singapore, which PVN then applied to set aside. It argued that the award breached the rules of natural justice because the decision on the validity of the Second Termination Notice was based on arguments that the parties did not raise and did not have the chance to respond to.
The Singapore High Court agreed that the award was made in breach of natural justice. However, it decided to remit the award to the tribunal, rather than set aside the award. It did so on the basis that:
The decision is significant as it demonstrates the utility of the power to remit awards, rather than set them aside, in appropriate cases. It is also a reminder to parties looking to bring tactical challenges that even where natural justice concerns are upheld, they may not necessarily result in an award being set aside. At the same time, it is also another reminder to arbitrators that arguments must be in play if they are to form any part of the reasoning in an award.
出版物
In this edition, we focused on the Shanghai International Economic and Trade Arbitration Commission’s (SHIAC) new arbitration rules, which take effect January 1, 2024.
出版物
The 28th Conference of the Parties on Climate Change (COP28) took place on November 30 - December 12 in Dubai.
出版物
On 8 September 2024, the Ministry of Commerce (MOFCOM), the National Health Commission (NHC) and the National Medical Products Administration jointly released the Notice on Carrying Out Pilot Programs to Expand the Opening-up in the Healthcare Sector (关于在医疗领域开展扩大开放试点工作的通知) (the Notice) .
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2023