Publication
Generative AI: A global guide to key IP considerations
Artificial intelligence (AI) raises many intellectual property (IP) issues.
Australia | Publication | 六月 2024
This article was co-authored with Michael Gu.
In Cessnock City Council v 123 259 932 Pty Ltd [2024] HCA 17 (Cessnock City Council), the High Court of Australia has provided welcome guidance as to when a party to a contract can recover its wasted expenditure incurred in anticipation of, or reliance on, performance of the contract by the other party.
This update provides a brief overview of the principles considered by the High Court and discusses the practical implications of the decision on drafting clauses to exclude liability for wasted expenditure.
As part of an initiative to develop Cessnock Airport, Cessnock City Council (Council) entered into an agreement for lease (AFL) with a company then-known as Cutty Sark Pty Ltd (Cutty Sark), by which Cutty Sark was to lease a prospective lot on the airport land.
The grant of the lease required subdivision of part of the Council's land and, accordingly, a term of the AFL was that the Council would take all reasonable action to apply for, and obtain, registration of the plan of subdivision by a certain date.
The Council breached that term and repudiated the AFL. Cutty Sark never obtained a lease.
By that time, Cutty Sark had spent considerable money in anticipation of, or reliance on, the Council performing its obligations under the AFL, by constructing an “iconic” aircraft hangar on the site of the proposed lot.
Cutty Sark’s businesses failed and, following the Council's breach and repudiation of the AFL, the AFL was terminated by Cutty Sark.
Cutty Sark commenced proceedings seeking damages for its wasted expenditure in constructing the hangar.
The aim of contractual damages is to put the claimant in the position it would have been in had the contract been performed. This is the rule from Robinson v Harman1, and reflects the principle that expected performance is the essence of Australian contract law.2
Accordingly, contractual damages are ordinarily calculated by reference to the benefit or profit that the claimant would have obtained had the contract been performed, but which has been lost as a result of the breach of contract. This type of loss is known as “expectation loss”.
A claimant always bears the legal onus of proving the benefit or profit, if any, it would have made if the contract had been performed. But what if, because of the defendant’s breach, there is uncertainty as to whether the claimant would have received a benefit or made a profit?
In Cessnock City Council, Cutty Sark could not prove whether it would have made a profit (and thereby recouped its expenditure on the hangar) from the businesses conducted from the hangar. Due to the Council’s failure to have the plan of subdivision registered, in breach of the AFL, the following matters necessary to prove Cutty Sark’s potential profit were uncertain and depended entirely on speculation:3
As a result, following the leading High Court cases of McRae4 and Amann Aviation5, Cutty Sark claimed contractual damages assessed as:
The question for the High Court was whether, in order for Cutty Sark to be awarded damages for its expenditure on the hangar, Cutty Sark needed to prove that it would have recouped that expenditure if the Council had obtained registration of the plan of subdivision and the lease had been granted, so that expenditure could properly be said to have been “wasted” by the breach.6
This is because all contractual damages seek to put the claimant in the position it would have been in if the contract had been performed. This is the principle from Robinson v Harman and is the “sole, obvious, and justified measure” of compensation for breach of contract in Australia7. This principle still applies in circumstances where the claimant cannot prove the benefit or profit it would have obtained due to the uncertainty created by the defendant’s breach. A majority of the High Court made it clear that the aim of contractual damages is not to put the claimant in the position it would have been in if the contract had not been made.8
The High Court unanimously held that Cutty Sark could recover as damages its wasted expenditure of $6.2 million (including interest) incurred in constructing the hangar.
Cessnock City Council has clarified that:
In the circumstances, as the Council's breach of contract had caused sufficient uncertainty about the position Cutty Sark would have been in had the contract been performed, Cutty Sark was to be taken to have established its loss as the amount it had expended on the hangar. That is, the expenditure was taken to have been incurred in anticipation of, or reliance on, the performance of the Council's obligation to obtain registration of the plan of subdivision, and which was wasted due to the Council’s breach of contract.
The High Court also relied on the above reasoning to settle some other issues that had been left open by its previous decisions:
To the extent that some, or all, of the expenditure would not have been recoverable had the contract been performed, those amounts will not be recoverable as damages from the defendant. Once the claimant establishes that it has incurred expenditure in anticipation of, or reliance on, the defendant’s performance of the contract, the defendant bears the evidential burden of proof of showing that some, or all, of that expenditure would not have been “wasted”14. The defendant’s task is likely to be a difficult one.
For example, in Cessnock City Council, the High Court held it was not enough to provide that there was a “prospect” that Cutty Sark would not have recouped its expenditure on the hangar.15 Nor was the fact that Cutty Sark had made actual losses (in the three years it had operated businesses from the hangar) enough to prove that Cutty Sark would not have recouped its expenditure, given the 30 year term of the lease which would have been granted.
The High Court has not excluded the possibility of a defendant proving that the claimant would only have recovered some lesser amount of its total expenditure. In Amann Aviation, the High Court majority held that it was appropriate to consider whether the contract between the parties would have been lawfully terminated, or whether it would not have been renewed, so the claimant would not have recovered the entirety of its expenditure. On the facts of that case, however, the High Court majority resolved both of these questions in the claimant’s favour on the balance of probabilities.16 The Council did not run a similar argument in Cessnock City Council.17
The Council was ultimately liable for $6.2 million (plus costs), comprising the cost of constructing the hangar ($3.7 million) plus interest.
By comparison, in choosing to breach and repudiate the AFL, the Council had relied on an estimate that expenditure of $1.3 million would have been required to be incurred by the Council to comply with the conditions enabling registration by the agreed date.
Cessnock City Council is therefore a salutary reminder that parties who try to avoid their obligations under an inconvenient or unprofitable contract may become liable for more than they initially contemplated.
Yes. Cessnock City Council has not disturbed the long-standing position that the scope of an exclusion clause is ordinarily a matter of commercial negotiation. Exclusion clauses are construed like any other contractual term – objectively. The question is what a “reasonable businessperson would have understood” its meaning to be18, by reference to “text, context … and purpose”.19
This approach prevails even if the expenditure specifically excluded relates to the “main purpose” of the contract. Some courts have suggested a narrower construction may be warranted, which can involve the rejection of “words, indeed whole provisions, if they are inconsistent with … the main purpose”.20 But the prevailing position is that an exclusion that denies the “main purpose” of a contract will still be effective if that is its true construction.21
Contracts often include general exclusion clauses that seek to oust liability for losses that might otherwise be recoverable under the general rule of “remoteness”. The High Court in Cessnock City Council confirmed that the ordinary rule that contractual damages are only recoverable if they are not too remote remains an effective control on the damages a claimant can recover for wasted expenditure.22 Contractual damages are not too remote if the amount claimed relates to either: “loss arising in the usual course of things from such breach as occurred”, or loss that “may be supposed to have been in the parties’ contemplation, when they made the contract, as the probable result of breach”.23
In Cessnock City Council, the High Court found that the wasted expenditure was not too remote as the Council was aware that Cutty Sark intended to construct a hangar on the proposed lot – it had granted development approval for a new hangar, and had permitted Cutty Sark to commence construction before the AFL was entered into.24 The AFL also contained “extensive provisions” in relation to the construction of the hangar.25 Accordingly, whether the Council could avoid liability for Cutty Sark’s loss associated with construction of the hangar was a matter of ordinary construction of the exclusion clause contained in the AFL.
It is a common drafting technique for general exclusion clauses to contain general expressions such as “indirect” or “consequential” loss to exclude losses for which parties would be liable because they are not too remote.
These general expressions (which appeared in the AFL) are notorious for having an objective meaning that contracting parties may not subjectively have intended. The authorities in this area are unsettled. Some Australian courts have held the term “consequential loss” ordinarily includes expenses incurred by a party.26 Other Australian courts have considered that this is not a fixed and inflexible rule.27 In England, the opposite is true – "wasted expenditure” is an “obvious and common” type of loss, so in order to be excluded, an exclusion clause should make express reference to it, or words to similar effect.28 As a result, an exclusion clause for “indirect” or “consequential” loss may not always cover wasted expenditure.
Instead, an appropriately drafted provision of a contract can exclude or limit damages for wasted expenditure provided that is what it clearly and unambiguously provides. We identify some relevant considerations below.
A general exclusion clause may be effective to exclude liability for wasted expenditure if, in addition to open-textured expressions such as “indirect” or “consequential” loss, it instead adopts the formulation for liability from Cessnock City Council, and refers to loss incurred by a party “in anticipation or reliance on performance” of the contract.
In addition, when parties to a contract contemplate that certain kinds of expenditure will be incurred, parties may be able to rely on a specific exclusion clause that expressly refers to those discrete kinds of expenditure, carefully drafted with regard to how each party intends to rely on the contract, and the expenditure they intend to incur. A clause is more likely to be effective to exclude wasted expenditure if it states, with specificity, the categories of expenditure in the contemplation of the parties.
The AFL did contain a “release” provision that attempted to exclude specific kinds of loss. While the relevant provision of the AFL made reference to discrete matters such as “the Aerodrome or Aerodrome Infrastructure Facilities not being available for use by [Cutty Sark]”, the “loss of [Cutty Sark’s] profits”, and “any change in the flow of members of the public in or around the Land or Aerodrome for any reason”, it did not make specific reference to Cutty Sark’s expenditure on the hangar and therefore such losses were found not to be caught by the exclusion.29
Cessnock City Council is therefore a reminder to take particular care to ensure that exclusion clauses are drafted to exclude wasted expenditure, if this is what is intended by the parties.
The High Court in Cessnock City Council confirmed that only reasonable expenditure incurred in reliance on a contract is recoverable. This includes expenditure that might “naturally be incurred in preparing for, performing, or exploiting the benefit of the contract, or that is or ought to have been contemplated by the defendant”.30
While it is not clear how reasonableness adds to the ordinary enquiry as to whether a loss is too remote (see above),31 it is likely that consideration of whether an amount is reasonable is relevant to the amount or extent of expenditure incurred, rather than the type of loss incurred.
For example, in Cessnock City Council, the Council was aware that Cutty Sark would undertake construction of an “iconic” hangar that would cost “around $1.8 million”.32
In circumstances where a counterparty will not agree to exclude wasted expenditure entirely, a limitation or cap on liability may be appropriate.
Publication
Artificial intelligence (AI) raises many intellectual property (IP) issues.
Publication
We are delighted to announce that Al Hounsell, Director of Strategic Innovation & Legal Design based in our Toronto office, has been named 'Innovative Leader of the Year' at the International Legal Technology Association (ILTA) Awards.
Publication
After a lacklustre finish to 2022 when compared to the vintage year for M&A that was 2021, dealmakers expected 2023 to see the market continue to cool in most sectors, in response to the economic headwinds of rising inflation (with its corresponding impact on financing costs), declining market valuations, tightening regulatory scrutiny and increasing geopolitical tensions.
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2023