Publication
International arbitration report
In this edition, we focused on the Shanghai International Economic and Trade Arbitration Commission’s (SHIAC) new arbitration rules, which take effect January 1, 2024.
Global | Publication | enero 2025
Following the Department for Energy Security and Net Zero’s (DESNZ) October 2024 announcement on a proposed cap and floor regime for Long Duration Electricity Storage (LDES), Ofgem published its ‘call for input’ on the LDES Cap and Floor Regime on 18 December 2024 (Call for Input).
In our previous briefing on the October 2024 publication, which was referenced in the recent House of Lords Committee Report on the proposed LDES scheme, we highlighted the need for more detailed information about the design and operation of the proposed LDES cap and floor regime. The Call for Input offers some clarity on Ofgem’s current thinking on specific aspects of the regime's design and invited feedback from stakeholders.
Ofgem’s proposals for its initial design cover the following areas, each of which is summarised below:
Ofgem plans to manage the LDES cap and floor regime through application windows. Key points include the following:
Ofgem will use a range of criteria to assess the eligibility. The Call for Input indicates that only projects that meet these criteria will progress to the Project Assessment stage which will involve a greater level of scrutiny.
Ofgem’s initial proposed eligibility criteria for Window 1 is:
The Call for Input sets out that Ofgem will assess developers' cost submissions to set preliminary cap and floor values, ensuring projects are economically efficient. As is the case for the regime supporting electricity interconnectors, this will involve reviewing procurement processes and detailed cost evaluations. To incentivise developers, Ofgem is considering performance-based incentives for cost-efficiency and timely delivery, and penalties for delays and cost overruns. In addition, projects must meet delivery 'backstop' dates in the 2030 and 2033 tracks (two years after the required delivery date) to retain support.
The proposed assessment process includes two stages: Project Assessment (PA) and Post Construction Review (PCR). Preliminary cap and floor levels will be set at PA and finalised at PCR. Developers will be required to submit annual reports during construction and yearly operational reports post-construction. Contingency allowances manage cost uncertainties, and developers must have mitigation plans for consumer-underwritten risks. High Impact Low Probability risks will be reviewed separately.
Ofgem is considering setting the floor for LDES projects at 80% of allowable project costs, as it does for interconnectors, and is considering two methods for setting such cap and floor:
The Call for Input provides useful further clarity on the direction of travel in many areas. There are, however, remaining gaps which will need to be filled in as further documents are published, including the TDD. One critical area requiring urgent clarification is the anticipated approach to perceived risks of gaming and market manipulation.
A range of options are considered in the Call for Input including (i) mandating LDES cap and floor projects to participate in the Capacity Market as price takers and bidding their full capacity into auctions and (ii) the possibility of requiring LDES assets to be operated by third parties rather than in-house teams. If adopted, these would represent significant constraints on the operation of LDES assets. As a result, additional clarification on Ofgem’s proposed approach will be closely monitored by the market.
The 8 January 2025 deadline for responses to the Call for Input has now passed and Ofgem, in collaboration with DESNZ, is expected to provide additional details and ‘next steps’ over the coming months.
Publication
In this edition, we focused on the Shanghai International Economic and Trade Arbitration Commission’s (SHIAC) new arbitration rules, which take effect January 1, 2024.
Publication
On September 18, 2024, the "Decree amending the list that sets forth goods whose import and export are subject to regulation by the Ministry of Energy" (the "Decree") was published in the Federal Official Gazette.
Publication
On September 18, 2024, the "Decree amending the list that sets forth goods whose import and export are subject to regulation by the Ministry of Energy" (the "Decree") was published in the Federal Official Gazette.
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2025