|
COVID-19-related project scenario |
Possible contractual remedies
|
1 |
Government (national/local) does not issue new legislation/regulations stopping construction works/activities on sites.
Due to health and safety measures being implemented to stop transmission of the virus, the contractor faces difficulties:
- Mobilizing personnel; or
- Obtaining materials due to issues in supply chain.
|
Time: The contractor may explore
- SC 8.4(d) of RB 1999, YB 1999 and SB 1999
- SC 8.5(d) of RB 2017, YB 2017 and EB
- SC 9.3(d) of Gold Bk
Which provide for EOT entitlement in cases of “Unforeseeable shortages in the availability of personnel or Goods (or Employer-Supplied Materials, if any) caused by epidemic or governmental actions” (RB 2017 wording).
Under SB 2017, the contractor is entitled to EOT only in the event of Unforeseeable shortages in the availability of Employer-Supplied Materials, if any, caused by epidemic or governmental actions.
There is no similar provision under SB 1999 as it is a Contractor’s risk under this Book.
There is no similar provision under Green Bk 1999 but SC 6.1(h), 7.3 and 10.4 could be investigated.
Money: The above provisions only give entitlement to EOT; there is no mention of financial remedy, which would depend on particular circumstances and whether the contractor can establish entitlement to financial compensation elsewhere under the contract or at law.
|
2 |
Government (national/local) does not issue new legislation/regulations stopping construction works/activities on sites.
Due to health and safety measures being implemented to stop transmission of virus, the contractor suffers delay which is caused by the authorities (for example, the authorities make repeated health and safety inspections of the site).
|
Time: The contractor may be entitled to an EOT under
- SC 8.5 of RB 1999, YB 1999, SB 1999 and PB
- SC 8.6 of RB 2017, YB 2017, SB 2017 and EB
- SC 9.5 of Gold Bk
Provided that conditions set out in the sub-clauses are fully satisfied.
Money: Regarding any financial entitlement, the same comment applies as in Scenario 1 above.
|
3 |
Government (national/local) has issued a change in the law (CIL) which restricts construction works/activities on sites.
The contractor is still able to proceed with works – but suffers delay and/or additional cost as a result of the CIL.
|
What constitutes a CIL in the relevant country?
CILs may include specific COVID-19-related measures affecting construction projects (examples include social distancing, supply of face masks and hand sanitizers, alternative arrangements for transportation, facilities, working hours for staff and labour).
Obtain expert legal advice on what particular events constitute CILs (for example, whether they include the introduction of new laws, modification of existing laws, judicial interpretation of laws or official governmental interpretation of laws).
FIDIC’s broad definition of “Laws” means that emergency laws/decrees being issued in different jurisdictions around the world are likely to constitute CILs.
This definition also extends to cover regulatory actions from “any legally constituted public authority” and can therefore apply to national parliamentary acts and state-wide actions as well as municipal orders at local levels.
In relation to CILs, the contractor may look to
- SC 13.7 of RB 1999, YB 1999, SB 1999 and PB (see contractor’s obligation to comply with applicable Laws at SC 1.13)
- SC 13.6 of RB 2017, YB 2017, SB 2017, EB and Gold Bk (see contractor’s obligation to comply with applicable Laws at SC 1.12 SB 2017/1.13 EB/1.14 Gold Bk)
CILs may also be treated as variations owing to any “adjustment to the execution of the Works” they may cause or to the “changed or new applicable standards” which they may constitute. Alternatively, CILs may be treated as claim events.
|
4 |
Government (national/local) has issued order(s)/decree(s) that prevent construction works/activities on sites.
Such order(s)/decree(s) may include lockdowns, curfews or quarantined areas (that become inaccessible).
It becomes impossible to carry on with the works on site and the contractor (and possibly even the employer) is unable to perform its obligations under the contract.
|
Consider whether Scenario 3 above in relation to CILs applies.
Alternatively, consider whether the scenario invokes the Force Majeure (in the 2017 suite, an “Exceptional Event”) provisions: whether the event/circumstance is one which:
- Is beyond the party’s control
- The party could not reasonably have provided against before entering into the contract
- Having arisen, the party could not reasonably have avoided or overcome
- Is not substantially attributable to the other party
Consider the following FIDIC clauses:
- SC 19.1 of RB 1999, YB 1999, SB 1999 and PB
- SC 1.1.14 of Green Bk
- SC 18.1 of RB 2017, YB 2017, SB 2017 and EB
- SC 1.1.37 of Gold Bk
The above clauses give examples of what might qualify as Force Majeure/Exceptional Event. The examples at the beginning of SC 19.1/SC 18.1 are of man-made events; the last example covers “natural catastrophes.”
Pandemics and local authorities/governmental actions are not specifically listed. A government ban on construction activities may enable a party to argue Force Majeure/Exceptional Event, but it would still need to pass the test in the clause such that the party arguing so “could not reasonably have avoided or overcome” the event.
A successfully claimed Force Majeure/Exceptional Event excuses performance of the said prevented obligations, provided the correct notifications have been given:
- SC 19.2 of RB 1999, YB 1999, SB 1999 and PB
- SC 13.2 of Green Bk
- SC 18.2 of RB 2017, YB 2017, SB 2017, EB and Gold Bk
Time: The contractor may be entitled to an EOT for any resulting delay:
- SC 19.4 of RB 1999, YB 1999, SB 1999 and PB
- SC 7.3 of Green Bk
- SC 18.4 of RB 2017, YB 2017, SB 2017, EB and Gold Bk
Money: Financial entitlements are more likely to flow from CILs (see Scenario 3 above) than from Force Majeure/Exceptional Events.
|
5 |
Government (national/local) has issued order(s)/decree(s) that prevent construction works/activities on sites.
Such order(s)/decree(s) may include lockdowns, curfews or quarantined areas (that become inaccessible).
It becomes impossible to carry on with the works on site and the contractor (and possibly even the employer) is unable to perform its obligations under the contract.
Can the contractor turn to Clause 17 (1999 – Risk and Responsibility/2017 – Care of the Works and Indemnities) in search of financial compensation (in addition to seeking an EOT)?
|
This Scenario builds upon Scenario 4 above.
Under Clause 17 of both the 1999 edition and the 2017 suite, a pre-condition to relief is damage or loss to the works. It is unlikely that the pandemic will cause loss or damage to the “Works, Goods or Contractor’s Documents”. Clause 17 is therefore unlikely to apply to Scenario 5.
It is more likely that the consequences of the pandemic will delay and disrupt the project, for which the FIDIC forms provide remedies in Clause 19 (RB 1999, YB 1999, SB 1999 and PB) and Clause 18 (RB 2017, YB 2017, SB 2017, EB and Gold Bk), as outlined in Scenario 4 above.
|
6 |
The contractor is able to proceed, but the pandemic is having an adverse impact on the progress of the works (this Scenario encompasses Scenarios 1, 2 and 3 above).
Government (national/local) does not issue new legislation/regulations stopping construction works/activities on sites. But, due to health and safety measures being implemented to stop transmission of the virus, the contractor:
- Faces difficulties
- Mobilizing personnel; or
- Obtaining materials due to issues in supply chain; or
- Suffers delay which is caused by the authorities (for example, the authorities make repeated health and safety inspections of the site)
OR
Government (national/local) has issued a change in the law (CIL) which restricts construction works/ activities on sites.
The contractor is able to proceed with the works, but suffers delay and/or additional cost as a result of the CIL.
Under Scenarios 1, 2 or 3, can either party turn to Clause 19 Force Majeure (1999 edition or PB)/Clause 18 Exceptional Events (2017 suite or EB)/Clause 18 Exceptional Risks (Gold Bk)?
|
In each of Scenarios 1, 2 and 3 above, the performance of obligations under the contract will become harder and more onerous, but will not necessarily be prevented. It is likely that the contractor will able to continue on site and reasonably overcome the events contemplated. Scenarios 1, 2 and 3 are therefore unlikely to qualify as Force Majeure/Exceptional Events.
Where the employer/engineer suspends part or all of the works (under Clause 8), as a precautionary measure, this is unlikely to result in Force Majeure/Exceptional Event (particularly in the absence of a CIL), but the contractor would be able to look to the remedies available under SC 8.9 of RB 1999, YB 1999, SB 1999 and PB, SC 7.3 and 10.4 of Green Bk, SC 8.10 of RB 2017, YB 2017, SB 2017 and EB, and SC 9.8 of Gold Bk.
In addition:
- During any suspension of activities, the contractor is under an obligation to protect, store and secure the works against any deterioration, loss or damage. The parties should therefore discuss how this obligation can be fulfilled.
- Note that removing the contractor’s right of access to the site may trigger remedies, as contemplated under SC 2.1.
|
7 |
There is no direct impact on the contractor’s operations, but the employer (or the employer’s representative/engineer) is working from home.
In this scenario, there is no CIL and no real impact on the availability of personnel or on the supply chain. However, members of the employer’s/employer’s representative’s/engineer’s organisation are working remotely and away from the site.
As a result of this, the contractor suffers delay/additional cost because of slow decision-making.
|
Time: The contractor may turn to provisions of the contract that provide an EOT entitlement in the event of delay, impediment or prevention caused by or attributable to the employer/employer’s representative/engineer:
- SC 8.4(e) of RB 1999, YB 1999 and PB
- SC 8.4(c) of SB 1999
- SC 6.1(k) and 7.3 of the Green Bk
- SC 8.5(e) of RB 2017, YB 2017 and EB
- SC 8.5(c) of SB 2017
- SC 9.3(e) of Gold Bk
Money: The above provisions only give entitlement to EOT; there is no mention of financial remedy, which would depend on particular circumstances and whether the contractor can establish entitlement to financial compensation elsewhere under the contract or at law.
|
|
|
|