What if your existing contract is affected?
Protect your rights when negotiating an interim solution
COVID-19 is likely to affect all businesses across all industry sectors. In some cases, both parties to a contract may be in breach of its terms due to COVID-19, and each will certainly have its own concerns regarding business continuity.
Accordingly, many businesses will first attempt a negotiated interim solution. If you are exploring this option, carefully consider how to do so without compromising your rights. For example, you may lose contractual rights if you fail to notify the counterparty promptly of your intent to exercise them.1
Force majeure
If performance of a contract is affected by COVID-19, you may be able to rely on the contract’s force majeure clause, if one has been included.
The purpose of force majeure clauses is to protect the parties from events that are agreed to be outside normal business risk. Force majeure clauses excuse the performance of contractual obligations if specified events outside the parties’ control have prevented such performance. If successfully invoked, the clause relieves a party from the performance of its obligations under the contract, thereby avoiding a breach.
Unlike some jurisdictions, ‘force majeure’ is not a legal doctrine in Australia. It is a contractual right only, meaning that whether a ‘force majeure event’ excuses performance of obligations is wholly dependent on the wording of the relevant clause(s) of the contract.
The following points are relevant when seeking to rely on a force majeure clause to avoid what would otherwise be a breach of contract during the current pandemic:
- Has a force majeure event occurred under your contract? Some contracts use a laundry list of potential occurrences and some simply refer generically to unforeseeable events beyond the control of the affected party. Clauses that reference pandemics and/or governmental action may be of particular assistance.
- Force majeure clauses are typically interpreted strictly. This may require some very granular thinking. For example, some clauses refer to “acts of God” (an event arising exclusively due to natural causes, without human intervention, and which cannot be foreseen or prevented2). While COVID-19 itself may potentially be classified as an act of God, it is questionable whether governmental responses to COVID-19 would qualify.
- What obligations are affected, and how seriously? A party seeking to rely on a force majeure clause is typically required to mitigate the impact of the force majeure event to the extent possible, even if this proves challenging. It is also crucial to identify which contractual obligations are affected by the force majeure event, and to what degree. Force majeure provisions usually specify that the party must be “prevented” from performing its obligations, or that it must be “impossible” or illegal for it to do so; it is generally not sufficient if it would instead only be more difficult or more expensive.
- What is the effect of invoking the clause? Typically, a force majeure clause excuses a party from performing affected obligations while the force majeure event continues, but unaffected obligations may still remain enforceable. For example, it would be particularly important to consider the implications in respect of payment obligations.
- Have you complied with the force majeure clause’s procedures? You may not be able to rely on the clause if you do not adhere to its requirements, particularly a requirement to notify the other party within a certain time.3
Is the contract frustrated?
If you cannot perform a contract because of a radical change in circumstances, so radical that the situation is now fundamentally different to what the parties had in mind, the contract may be discharged for frustration.4
A contract is not frustrated if it merely becomes more difficult or expensive to perform. Because the parties’ precise arrangements and communications are highly relevant, the same incident could frustrate some contracts but not others.
For example, a wave of contract cases ensued from delays to the coronation of King Edward VII in 1902. Some contracts were not frustrated (eg. a planned naval fleet tour could proceed as a day cruise even though the coronation was delayed), whereas others were frustrated when the contract’s underlying purpose was destroyed.5
At common law, a frustrated contract is terminated automatically, but this does not affect rights and obligations accrued before termination. However, discharge for frustration is governed not only by common law, but also by legislation in several States.6 Obtaining a complete picture of potential rights and obligations if a contract is frustrated therefore requires reference to the contract’s governing law.
Consequences of incorrectly invoking a force majeure clause or claiming frustration
It is important to be clear about the basis of your rights before invoking a force majeure clause or claiming that a contract is frustrated. Doing so invalidly may be deemed a repudiation of the contract and may give the counterparty the right to terminate and claim damages for the loss of the benefit of the contract.
To ensure a consistent strategy is employed with full recognition of the ramifications, including the various reputational and conduct risks, we recommend considering what internal controls will apply to such decisions, and whether a business-wide approach can be implemented.
In the current crisis conditions, both government and the business sector has stressed the need for business (and relationship) continuity, where possible. This thinking also applies to exercising force majeure. Working through the possible consequences of a decision is critical: for example, what might be the status of your business relationship with your counterpart post-force majeure? Is there a possibility of brand damage if you are perceived to exercise force majeure “unfairly”?
In addition, regulated businesses (that are considering force majeure exercise) need to be aware that regulators will be looking closely at commercial decision-making in the current circumstances. How a business’ conduct risk is managed (eg. was the question “should we do this?” asked in relevant circumstances) will be a matter of acute concern for many regulators as they pursue their risk-based supervision mandates.
Avoiding and resolving disputes when force majeure is invoked
The most common area of dispute when force majeure is invoked is whether the contract’s force majeure clause in fact captures the event that has occurred. Accurately and contemporaneously documenting both the direct effects of the event (including their duration) and your communications with the counterparty are critical. At the height of the crisis, a party may give acknowledgements of its consequences from which they might seek to resile after it has passed.
Generally, a refusal to accept that there is force majeure (or a claim that it is applicable which is rejected) will constitute a dispute which must be resolved using the process specified in the contract (if any). Ideally, this will require good faith negotiations, and possibly a mediation, before court or arbitral proceedings can be commenced. Even if it does not, the Federal Court and State Court legislation and rules generally oblige parties to explore settlement options before the issue of proceedings.
Resolution of disputes of this nature by informal means or by mediation is consistent with the current business and societal imperative to work co-operatively to maintain normal activity and preserve economic structures as far as possible. If an appeal to your counterparty in those terms does not work, it might be worth pointing out to them that the courts are all basically closed now for the duration anyway!
Negotiating new contracts during the pandemic
Don’t rely on frustration for new contracts
A contract is not frustrated if the parties could reasonably have foreseen the change in circumstances.7
Exactly when the implications of COVID-19 became sufficiently foreseeable to defeat a claim of frustration could well become the subject of future litigation. However, COVID-19 and its many potential associated disruptions are at least now clearly foreseeable.
Don’t leave everything to force majeure
It is impossible to know exactly how COVID-19 may continue to affect Australian businesses, but we can take some instruction from the experience in other nations with higher infection counts, as well as public health experts’ predictions.
Accordingly, we recommend including contingencies (ie. cascading provisions dealing with different scenarios) to respond to various COVID-19 related escalations. This approach minimises the risk that you cannot rely on a specific force majeure event, and it also allows the parties to agree tailored solutions rather than relying on a comparatively generic force majeure clause. In effect, terms are drafted which set out the rights and obligations of the parties during the interim period and provide a roadmap to get back to normality once the pandemic abates.
Exactly what events to account for in such provisions will depend on the industry and the nature of the contract, but may include:
- one or both businesses are required to close or operate in a different manner under governmental “lockdown” directives or elect to close in accordance with non-binding governmental advisories; and
- one or both businesses need to temporarily cease operations because of an infection or may choose to do so on a precautionary basis.
Getting back to normality
The current climate is not permanent, but restrictions may ease only gradually and could be re-introduced if a subsequent outbreak occurs. As part of any contractual negotiations consider:
- whether any unusually flexible or restrictive terms will revert to market standard once the crisis abates?
- if so, what should your contract say about how it will be determined that sufficiently normal conditions have returned? Each nation, and indeed each Australian State and Territory, will have its own recovery trajectory, so any international or interstate touchpoints in the contractual arrangement may affect this determination.
- will emergency provisions be re-introduced if there is a further outbreak? How will these be triggered under the contractual terms?