Introduction
This article offers a cross-border update of recent jurisprudential and legislative
developments on challenges to arbitral awards in Singapore, Hong Kong, and
England and Wales.
Questions of jurisdiction
Does non-participation bar a
subsequent claim to set aside?
Recent jurisprudence in Singapore has
continued to explore the relationship
between Article 16(3) and Article 34 of
the Model Law.
Article 16(3) allows a party, where a
tribunal has made a preliminary ruling
that it has jurisdiction to hear the dispute,
to challenge that ruling before the courts
of the seat within 30 days of receiving
notice of the ruling. Article 34 provides
for the remedy of setting aside an award
on grounds including that the award
deals with a dispute not contemplated
by or not falling within the terms of the
submission to arbitration, or contains
decisions on matters beyond the scope of
the submission to arbitration.
In Rakna Arakshaka Lanka Ltd v Avant Garde
Maritime Services (Pte) Ltd [2019] SGCA 33
(Rakna) the Singapore Court of Appeal had to
consider whether a respondent who fails to
participate in an arbitration and therefore does
not avail itself of its rights pursuant to Article
16(3) to challenge a tribunal’s determination
that it has jurisdiction, can nevertheless raise
the jurisdictional objection before the
supervisory court in set-aside proceedings.
In the earlier case of PT First Media TBK v
Astro Nusantara International BV [2014]
1 SLR 372 (Astro) the Court of Appeal
held that properly construed, the Model
Law provides for the system of “choice of
remedies”, and parties who do not actively
attack an award remain able to passively
rely on defences to enforcement absent
any issues of waiver. The Court concluded
that the “preclusive effect” of Article 16(3)
does not apply where what is sought to
be achieved is a defence to enforcement,
rather than the active remedy of set-aside.
In dealing with the relationship between
the active remedy in Article 16(3) and the
active remedy of set-aside under Article 34,
the Court held obiter that Article 16(3) was
not intended to be a “one-shot remedy”.
In Rakna, the Court of Appeal was
concerned not only with the “preclusive
effect” of Article 16(3) on subsequent
set-aside applications, but also whether
the preclusive effect operates in all
circumstances. The Appellant argued that
even if Article 16(3) operates to preclude
a set-aside application on jurisdictional
grounds in circumstances where a party
has not availed itself of the appeal grounds
in Article 16(3), this preclusive effect
does not apply to a party that has not
participated in the arbitral proceedings.
On the basis of the travaux préparatoires
including the Analytical Commentary to
the Model Law, the Court held that “It is
clear that the drafters intended Art 16(2)
to have a preclusive effect and, in all
likelihood, intended the same effect for
Art 16(3).”
The Court then went on to analyze the
effect of non-compliance with Article 16(3)
on a non-participating party. The Court
found the policy objective underlying
Article 16(3) was to “effect a compromise
between the policy consideration of
avoiding wastage of resources … and the
policy consideration of preventing parties
from trying to delay arbitral proceedings
by bringing challenges before the court”.
In the Court’s view, the claimant who
insists on proceeding in the face of a
non-participating respondent who has
indicated its objection to the tribunal’s
jurisdiction, must take the risk of wasted
costs. In the absence of a clear duty on the
respondent to participate in the arbitration
proceedings imposed either by the Model
law or the International Arbitration Act,
a non-participating respondent should
not necessarily be bound by the award
no matter the validity of its reasons for
believing that the arbitration was wrongly
undertaken. The Court concluded that
Article 16(3) should not be construed as
having a preclusive effect to prevent a non-participating respondent from seeking
set-aside of the award.
As a result, it is possible to now articulate two
exceptions in Singapore to the “preclusive
effect” of Article 16(3) of the Model Law,
stemming from the jurisprudence. The first
is where a respondent exercises its “choice
of remedies” and relies on its jurisdictional
objection to resist enforcement of an award
(rather than seeking to have the award
set-aside). The second is in circumstances
where the respondent elects not to
participate in the arbitration, having made
known its objection to the tribunal’s
jurisdiction, it is not precluded from
seeking a set-aside of the award at the
courts of the seat.
What power does a court have
to review a tribunal’s finding
of no jurisdiction?
There has been a rare but notable example
of the English court’s exercise of its power
to review negative jurisdictional findings
of an arbitral tribunal under Section 67 of
the Arbitration Act 1996. In GPF GP Sàrl
v The Republic of Poland [2018] EWHC 409
(Comm), the Commercial Court set aside a
tribunal’s ruling that it lacked jurisdiction
to hear Fair and Equitable Treatment
(FET) claims and examine creeping
expropriation claims arising under the
Bilateral Investment Treaty (BIT) between
Belgium/Luxembourg and Poland.
Mr Justice Bryan granted the application,
and set aside part of the tribunal’s award,
substituting wording to the effect that
the tribunal did have jurisdiction over all
measures relied on by the applicant under
the BIT. On the expropriation claim, the
Court held that it was possible to have
regard to alleged creeping expropriation
even in circumstances that also allege
a directly expropriatory act. On the FET
claim, the Court held that the wording of
the relevant clause was concerned with
consequences rather than measures,
such that the tribunal has jurisdiction to
hear claims concerning measures other
than expropriation that could cause
consequences similar to expropriation,
as alleged in the FET claim.
Questions of time
Does a court have a discretion
to amend the time limit for a
set-aside application?
In its first arbitration-related judgment
to date, the Singapore International
Commercial Court has held in BXS v BXT
[2019] SGHC(I) 10 that it has no power
under Singapore law to extend the time
limit in Article 34(3) of the Model Law
for filing an application to set aside an
arbitral award. Anselmo Reyes IJ held that
on its face, Article 34(3) is a written law
that appears to impose a mandatory limit,
which therefore circumscribed the court’s
power to amend time limits. The Plaintiff’s
application to set aside was accordingly
struck out as being out of time.
Does a court have a discretion to
extend the time limit for enforcing
an award?
In CL v SCG, an award creditor who was
unsuccessful in enforcing an award in
China sought to enforce the same in Hong
Kong. However, whilst the enforcement
efforts were ongoing in China, no action
had been taken to enforce the award in
Hong Kong. In the judgment, it was held
that the limitation period for enforcement
of an award in Hong Kong (based on an
implied contractual obligation to honor
the award) is six years from when the
cause of action accrued. The time when
the cause of action accrued was when
the award debtor failed to honor the
implied obligation which the court held
to be 21 days from the date of the award
creditor’s demand based on the facts of
the case. The court further noted that this
limitation period is not changed in any
way by reason of the agreement for mutual
enforcement of arbitral awards between
Hong Kong and China, which prohibits the
taking of enforcement actions in the two
jurisdictions at the same time. Accordingly
the award creditor was time barred.
This case is a useful reminder for award
creditors, that where assets might be held
in multiple jurisdictions, a comprehensive
global enforcement strategy must be
devised. A thorough investigation
is needed as to the whereabouts of
assets, and enforcement efforts across
jurisdiction/s must be chosen strategically.
Questions of fraud, corruption and public policy
When is conduct fraud upon the
tribunal or just a forensic decision
as to evidence?
Public policy arguments made to set aside
awards and resist enforcement of awards
can coalesce around allegations of fraud
or corruption, including fraud upon the
tribunal. Allegations of this kind recently
emerged in BVU v BVX [2019] SGHC 69 in
which the Singapore High Court refused to
set aside an ICC award (that concerned a
food supply agreement in favor of a South
Korean state-owned entity) alleged to have
been procured by fraud or that it offended
public policy; in this case because of the
decision not to call upon a particular
witness. The purchaser decided in the
arbitration to only call one factual witness
and not to call three other individuals
involved in negotiations for the supply
agreement. Following the award, the
supplier reached out to one of these three
witnesses who agreed to provide evidence
attesting to the purchaser’s understanding
of the nature of the agreement. The supplier
submitted that the decision not to call this
witness constituted the “withholding and
suppressing [of] crucial evidence.”
The Court noted three requirements
for a finding of this kind (1) deliberate
concealment aimed at deceiving the
tribunal; (2) an absence of a good reason
for the non-disclosure and; (3) a causative
link between the concealment and the
decision favoring the concealing party.
On the facts, the Court rejected the
suggestion that there was deliberate
concealment, and strongly rejected any
causative link between the purchaser’s
alleged concealment and the award in
its favor. The Court held instead that the
decision not to call factual witnesses
was a legitimate forensic judgment as
to the evidential requirements in the arbitration. The Court made a distinction
between the exigencies of the adversarial
process and unconscionable conduct,
finding that the decision not to call upon
a particular witness, while deliberate, did
not constitute the fraudulent suppression
of evidence in the absence of a positive
obligation to do so. The Court noted that
the IBA Rules on the Taking of Evidence
in International Arbitration (IBA Rules) do
not create a general obligation to disclose
all potentially relevant materials; Article
3.1 requiring only that parties disclose
documents “available to it on which it
relies”. The decision once again affirms the
high threshold for setting aside an award
on these grounds.
Similar issues concerning alleged fraud
upon the tribunal were considered in
the English case of Carpatsky Petroleum
Corporations v PJSC Ukrnafta [2018] EWHC
2516 (Comm). In resisting enforcement
of the SCC award in England under
Section 103 of the Arbitration Act 1996,
the defendant argued that the award
had been obtained by fraud because a
witness, who had been cross-examined
in the arbitration, had deliberately
misrepresented the claimant’s financial
position. This allegation was said to be
supported on the basis of documents the
defendant had obtained subsequent to
the arbitration. CPC successfully applied
to strike out the fraud allegations on the
basis that the documents did not satisfy
the conditions in Westacre Investments Inc
v Jugoimport SPDR Holding Co Ltd [2000]
Q.B. 288, which required that (1) the
documents were not available before the
arbitrators or could not with reasonable
diligence have been available in time to be
raised before the tribunal and; (2) would
have been decisive where the fraud alleged
was that the witness was being dishonest
before the arbitrators.
Both cases point to a need for parties
and their counsel to take care to obtain
documentary evidence that they feel may
be important to their case in adequate time
to allow argument on the material before
the tribunal.
Questions of serious irregularity
When can an award be aside or
remitted for reconsideration due
to a serious irregularity?
In England and Wales there have been
three recent successful challenges on
the ground of serious irregularity under
Section 68 of the Arbitration Act 1996.
In Oldham v QBE Insurance (Europe)
Ltd [2017] EWHC 3045 (Comm), the
Commercial Court allowed a challenge
to an arbitral award on costs where the
applicant had not been given a reasonable
opportunity to make submissions as to
costs. In P v D [2017] EWHC 3273 (Comm),
the Commercial Court upheld a challenge
to an LCIA award on the basis that the
tribunal failed to deal with all the issues
that were put to it; in particular, it failed
to consider the claimant’s contribution
claim in the proceedings. Finally, in RJ and
another v HB [2018] EWHC 2833 (Comm),
the Commercial Court set aside an arbitral
award for serious irregularity due to the
tribunal’s failure to give the parties notice
and a proper opportunity to consider and
respond to a new point that ultimately
affected the arbitrator’s reasoning in
the award.
A series of recent decisions in Hong Kong
have also considered questions of serious
irregularity. The contracts that were the
subject of the arbitration were construction
contracts wherein certain claims advanced
by contractors were subject to contractual
requirements for notices to be given. Such
notices are often said to be conditions
precedent for claims being advanced
and must be strictly followed. In an
unpublished judgment of a Hong Kong
court, it was held that an arbitrator’s
finding that the notice requirements were
satisfied instead by letters and emails
issued by the contractor, without hearing
full submissions from the parties on the
issue, amounted to a serious irregularity
warranting remittance of the award back
to the arbitrator for reconsideration. The
approach of the Court was similar to that in the 2018 decision in Maeda Corporation v
Bauer Hong Kong Ltd where the Court held
that the arbitrator’s broad interpretation of
notice provisions for making a claim under
a sub-contract, that was a “like right”
claim under the main contract which was
said to have to be strictly complied with,
was open to serious doubt.
Questions of common law actions vs enforcement proceedings
Does the range of remedies differ
under common law actions?
Xiamen v Eton Properties is a 12-year
running case to do with the enforcement in
Hong Kong of a CIETAC award, not under
the Arbitration Ordinance but by way of
a common law action. The arbitration
concerned enforcement of an agreement
to sell the right to develop a plot of land.
The seller had breached an agreement to
sell the development right for the land,
and restructured the project vehicle so
as to render the purchaser’s right in the
vehicle to be substantially diluted thereby
frustrating the purchaser’s control over
the vehicle. The seller was unsuccessful in
the arbitration, and subsequently failed to
honor the award against it. The purchaser
therefore initiated an action against the
seller in the Hong Kong courts seeking
damages under common law, in lieu of
seeking specific performance of the award.
The purchaser failed at first instance.
On appeal, the Court of Appeal held that
whenever parties submit a dispute to
arbitration there is an implied contract to
the effect that the losing party will honor
the award. The seller was therefore in
breach of this implied contract and was
ordered to pay the purchaser damages for
breach of contract. The Court of Appeal
dismissed both parties’ applications for
leave to appeal further. In the dismissal
judgment, the Court held that the loss
and damage arising from a breach of the
underlying commercial contract and those
arising from breach of the implied contract
to honor the award could be different, and
in the enforcement action brought by the purchaser, the court was concerned with
the latter. One interesting observation
arising from this decision is that it has the
potential of opening up a whole range of
remedies against third parties who may
have procured or assisted in the award
debtor’s effort to frustrate the award
creditor’s ability to enforce an award. This
is particularly relevant in situations where
shareholders or affiliates of the award
debtor have taken steps to interfere with
the implied agreement to make the award
debtor somehow judgment proof.
Questions of multi-parties and multi-contracts
Rights of non-signatory third
parties
A recent Hong Kong case has demonstrated
that an arbitration agreement may well be
binding on a third party even though they
are not signatory thereto, particularly in
circumstances where a benefit is conferred
on a third party under the original contract
(here, a shareholder agreement) containing
the arbitration agreement. In Dickson
Valora Group v Fan Ji Qian, a Hong Kong
court granted Fan an anti-suit injunction
against a mainland individual restraining
him from commencing Chinese court
proceedings to claim a success fee based on
an addendum to a shareholder agreement
among three joint venture partners for the
development of a property project in China.
Fan was successful in obtaining a freezing
order against the assets of the joint venture
vehicle and resisting the joint venture
vehicle’s challenge of the jurisdiction of the
Chinese court. The injunction was granted
on the basis that the addendum was to do
with Fan’s enforcement of a contractual
right under the shareholder agreement
even though he was not a signatory
thereto. The Court further held that the
judgment of the Chinese court was not
enforceable in Hong Kong and did not bar
the Hong Kong court from deciding any of
the issues before it.
Award involving multiple contracts
In Buda Pipe Rehabilitation Engineering
v CPC, a Hong Kong court dismissed
an application to challenge an award
(on grounds of an error of law) on the
basis that Schedule 2 of the Arbitration
Ordinance did not apply to the award as
there was insufficient indication that the
award was a domestic award. The Court
rejected the contention that the arbitration
provisions in the main contract between
the Water Services Department and an
affiliate of CPC (i.e. Lam Woo) could
be carried down into the sub-contract
between Buda and CPC pursuant to Section
101(1) of the Arbitration Ordinance. It
reasoned that there was a break in the
contractual chain between the employer
and Lam Woo, the agreement between
Lam Woo and CPC (which was only an
oral contract), and the sub-contract
between CPC and Buda with there being
no arbitration agreement in the agreement
between Lam Woo and CPC. By way of
obiter, the Court held that even if it was
wrong on the contractual chain issue, the
decision of the arbitrator in the Buda/CPC
arbitration was not obviously wrong to
warrant the court’s interference.
Questions of error of law
When is the obviously wrong
test the right test?
In the case of Chun Wo Construction &
Engineering v The Hong Kong Housing
Authority, the Court of Appeal has
confirmed the correct test for deciding
a leave to appeal application under
Schedule 2 of the Arbitration Ordinance
in respect of an error of law. The Court
held the test to be the “obviously wrong
test” in a one-off question of contractual
interpretation, as opposed to the “serious
doubt” test in respect of a question of
general importance. As to the “obviously
wrong” test, the Court of Appeal said
that the same will not be satisfied if the
arbitrator “might be right”. The judgment also noted that the interpretation of a
non-standard contractual provision will
likely be considered as not one of general
importance. The applicable test in an
appeal proper was stated by the Court in
a recent decision in Maeda Corporation
v Bauer Hong Kong Ltd to be whether the
arbitrator’s decision was one which “no
reasonable arbitrator could reach” or
“outside the permissible range of solutions
open to him” – i.e. the “obviously wrong”
and “serious doubt” tests no longer being
applicable.
Should Singapore amend its
International Arbitration Act to
allow an appeal on a point of law?
The law concerning challenge to awards
has recently been considered in the
legislative sphere in Singapore. The
Singapore Ministry of Law’s public
consultation on proposed amendments to
the International Arbitration Act includes
new proposals in this area. Of particular
interest is the proposal to allow parties
engaged in international arbitration seated
in Singapore to appeal to the High Court on
a point of law, provided they have agreed to
opt-in to this mechanism. (Parties engaged
in domestic arbitration in Singapore
already have the ability to appeal to the
High Court on a point of law but may
opt-out of this option by agreement.)
There is also a proposal to allow parties
to agree to waive or limit by agreement,
after the award has been rendered, the
annulment grounds under the Article 34(2)
(a) of the Model Law and Section 24 of
the International Arbitration Act. A third
proposal suggests empowering Singapore
courts to make an order in respect of the
costs of the arbitral proceedings when a
party is successful in its application to set
aside the arbitral award. The consultation
period closes on August 21, 2019.
Previous issues