Publication
Competition Act amendments hub
Since 2022, there have been three waves of amendments to the Competition Act resulting in the most significant revisions to Canada’s competition laws in over a decade.
Canada | Publication | August 2019
The National Energy Board (NEB) recently released its decision confirming that the proposed Coastal GasLink natural gas pipeline falls outside federal jurisdiction and as a result, neither the NEB nor its successor, the Canada Energy Regulator, will regulate it.
The NEB’s decision applies the test from the earlier Westcoast decision concerning projects located exclusively within a single province. Based on the specific purpose of the Coastal GasLink project and its level of integration with the larger NGTL System, including evidence of management, control and direction, neither branch of the Westcoast test was made out. Notably, however, the case diverges from an earlier BC pipeline decision involving facts similar to the Coastal GasLink project.
The Coastal GasLink Pipeline Ltd. project (CGL Project) is a 670-kilometre natural gas pipeline located entirely within British Columbia. It is designed to transport natural gas from the Western Canadian Sedimentary Basin (WCSB) to the LNG Canada marine export terminal (LNG Canada Terminal) in Kitimat. Natural gas produced from the WCSB is gathered and transported by the NGTL System, which is owned and operated by a subsidiary of TC Energy Corporation (TCE, formerly TransCanada PipeLines Limited). The larger NGTL System crosses the BC-Alberta border and is regulated by the NEB.
The CGL Project received its provincial environmental assessment certificate in 2014 and its permits from the BC Oil and Gas Commission for construction and operation in 2015. Construction is currently underway. TCE has not yet applied to connect the CGL Project to the NGTL System, but will do so in the future.
In 2018, the NEB received an application from Michael Sawyer, a BC resident, who requested that the board determine whether the CGL Project is within federal jurisdiction under section 92(10)(a) of the Constitution Act, 1867, and is regulated by the NEB under the National Energy Board Act. Mr. Sawyer argued that because TCE intends to eventually connect the CGL Project to the NGTL System, the CGL Project will extend beyond the BC border into Alberta, making it an interprovincial undertaking within federal jurisdiction.
A work or undertaking located wholly within a province is subject to federal regulation if it meets one of two key indicia established in Westcoast Energy Inc v Canada (National Energy Board):
Mr. Sawyer relied on the recent Federal Court of Appeal decision of Sawyer v TransCanada Pipeline Limited,2 in which he had successfully argued that the very similar Prince Rupert Gas Transmission Project (PRGT Project) fell within federal jurisdiction. Based on nearly identical circumstances, the Federal Court of Appeal determined in Sawyer that the PRGT Project, on its face, satisfied both branches of the Westcoast test. Just like the CGL Project, the (now cancelled) PRGT Project would have connected WCSB gas to a BC marine export terminal and have been wholly within BC.
Unsurprisingly in this case, Mr. Sawyer used the PRGT Project as a “blueprint” for his position and argued that both branches of the Westcoast test were met based on the fact the CGL Project and the NGTL System are functionally integrated, and TCE exercises common management, control and direction of NGTL and CGL.
In response, TCE argued it had neither applied to connect the CGL Project to the NGTL System, nor did the CGL Project meet either branch of the Westcoast test. TCE argued the CGL Project and NGTL System would not be functionally integrated, because they serve two different functions: the CGL Project serves the LNG Canada Terminal, whereas the NGTL System serves various customers in multiple locations.
Regarding management, control, and direction, TCE acknowledged it would manage both the CGL Project and the NGTL System, and would apply similar engineering standards, policies and procedures, and the expertise of its personnel to both. However, TCE argued this is not sufficient to conclude that the CGL Project and the NGTL System are subject to common management, control, and direction.
Following a public hearing with oral arguments from TCE and intervenors, the NEB released its decision on July 26 finding that:
The NEB rejected a number of other novel arguments made by participants in the hearing. Among other findings, the NEB determined there is no presumption of provincial or federal jurisdiction for a work or undertaking, because each case is determined on its own facts, and no presumption of deference to government actors arises on a jurisdictional analysis. Furthermore, a jurisdictional analysis does not incorporate a “reasonable person’s standard” or concept of environmental protection.
The NEB’s decision reflected the submissions of many energy industry actors, ranging from producers to offtakers to pipelines companies. Multiple provincial attorneys general also made submissions supporting provincial jurisdiction. The decision is likely to be appealed. Appellate arguments are likely to re-engage with how the NEB distinguished the PRGT decision and whether the CGL Project could be considered “vital” to the federal undertaking of international gas export.
Leave to appeal the NEB’s decision on jurisdiction to the Federal Court of Appeal must be sought by August 25, 2019.
Publication
Since 2022, there have been three waves of amendments to the Competition Act resulting in the most significant revisions to Canada’s competition laws in over a decade.
Publication
Since January 1, 2024, federal legislation in Canada requires companies of a certain size that produce, sell, distribute or import goods into Canada to file a report by May 31 each year regarding the risks of forced labour and child labour in their business and supply chains and the efforts taken to reduce those risks.
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2023