Publikation
Distress signals: Cooperation agreements or mergers to the rescue in times of crisis?
The current volatile and unpredictable economic climate creates challenges for businesses.
Global | Publikation | December 2015
On December 17, 2015, the Department of Energy & Climate Change (DECC) published responses to controversial consultations launched over the summer in relation to reductions in the support for renewable energy under the Feed-in Tariff (FiT) and the Renewables Obligation (RO) schemes.
Both schemes provide revenue support for renewable energy in Great Britain (GB).
The RO places an obligation on UK electricity suppliers to source an increasing proportion of the electricity they supply from renewable sources. Renewables Obligation Certificates (ROCs) are green certificates, issued to renewable energy generators, sold to suppliers and ultimately used by suppliers to demonstrate that they have met their obligation.
The FiT scheme is designed to support small scale renewables. It requires some suppliers to pay indexed tariff payments on both generation and export of renewable and low carbon electricity.
Both schemes have been victims of their own success. The Government has sought to limit projected overspend under renewable energy support schemes, to comply with the Levy Control Framework caps. Even if these cost control measures are implemented, the Government estimates that a total of 12.8GW of solar capacity will be deployed under the RO, FiTs and Contracts for Difference by 2020/21.
Moves to limit renewable energy deployment in the UK are in stark contrast to announcements made recently in the USA, where law makers agreed to extend tax credits for solar and wind for another five years.
For solar photovoltaic (PV) projects of 5 MWs and below and for additional capacity added to a project which does not take it above 5 MWs in total, the Government has decided:
Since the Government launched the original consultation on 22 July 2015, developers have rushed to build out their projects before the proposed RO closure date. Now that the decision is confirmed and with legislation is expected to hit the statute books by 1 April 2016, analysis of whether the grace period criteria have been met will become increasingly important for investors whose projects are on the margins.
Grandfathering is defined by DECC as “a statement of policy intent that once a generating station is accredited and receiving support under the RO at a certain level (or band), the level it receives […] would not change for the lifetime of its support under the RO.”
Whilst the announcement to end grandfathering for solar PV of 5MWs and below is disappointing for some investors, it does not affect projects that:
Other projects however will only obtain the rate of support which applies at the time of accreditation until the implementation of any proposed reduction in support. Therefore, projects accrediting after 22 July 2015 which did not meet the significant financial commitment criteria on or before that date, will not be grandfathered even if such projects either:
The Government has also launched a consultation on a reduction in support for all solar PV projects located in England and Wales, whether ground or building-mounted, of 5 MWs and below (or additional capacity where the total installed capacity does not exceed 5MWs) with an accreditation date of 23 July 2015 onwards. These changes do not apply in Scotland or Northern Ireland as banding levels are devolved matters and the Scottish Government and Northern Ireland Executive have elected not to undertake a banding review. The consultation closes on 27 January 2016, with changes expected to be implemented by 1 June 2015.
Affected projects would receive the lower band of 0.8 ROCs/MWh, effective from 1 June 2016. This means up to a 46% reduction in the level of support when compared to existing ROC bands for solar PV (see table below).
Ground-mounted | Building-mounted | Proposed Down-Banding | |
2015/16 (ROCs/MWh) | 1.3 | 1.5 | - |
2016/17 (ROCs/MWh) | 1.2 | 1.4 | 0.8 (effective from 1 June 2016) |
To try to maintain investor confidence, an exception is proposed where a project has met the significant financial commitment criteria, whether they accredit under the RO before or after the implementation of the banding review. All generating stations accredited on or after 23 July 2015 will need to provide the evidence detailed below to retain their level of support.
Meeting the criteria for a significant financial commitment on or before 22 July 2015 will be particularly important for investors. This will allow a project to:
The evidence required to demonstrate a significant financial commitment broadly comprises:
Litigation has already been announced in relation to the removal of grandfathering on the grounds that the UK government had given “clear and unambiguous assurances that it was committed to the principle of grandfathering”.
Separately, litigation commenced by Solar Century relating to the early closure of the RO to large scale solar PV will go to appeal in early February 2016. The outcome of the case will be important for small scale solar PV generators who will be interested in any ruling that the Government acted beyond the scope of the powers conferred under the Energy Act 2013 and contrary to developers’ legitimate expectations based on previous policy statements.
In relation to FiTs, the Government received 55,000 responses to the consultation, a testament to the strength of public opinion on the subject. The Government determined to:
Pre-accreditation gives generators a guaranteed tariff level in advance of commissioning their installation, provided a project is commissioned and full accreditation applied for within a specified time period, called the validity period. It was (and will be again) available to solar PV and wind of 50kW or more, hydro and anaerobic digestion. To qualify for pre-accreditation, a project must have planning consent and a grid connection agreement (and, for hydro installations, environmental permits). Validity periods are 6 months for solar PV, one year for wind, and two years for hydro and anaerobic digestion.
Given the introduction of caps, industry will be relieved that pre-accreditation is being reintroduced in its original form from 8 February 2016. DECC observes that these projects “will be able to “book” a place within a cap long before they are fully commissioned, reducing (although not removing) the risks associated with missing out on a cap”.
The changes to the FiTs are being introduced by the Feed-in Tariffs (Amendment) (No. 3) Order 2015 (FiT Order) and the Modifications to the Standard Conditions of Electricity Supply Licences 2015 No. 3 (Licence Modifications). The revised FiT Order is currently before Parliament and is subject to a minimum 21 day period before coming into force on 15 January 2016. Changes to the electricity licence conditions will take 40 days and so will only come into effect on 8 February 2016. As a result, to avoid a regulatory mismatch, the FiT regime will be paused for 4 weeks from 15 January 2016, during which time no new accreditations will be permitted (other than for schemes which pre-accredited prior to 1 October 2015 and are applying during their validity period).
Industry should brace itself for a further consultation on FiTs for anaerobic digestion and micro-CHP in early 2016. DECC have also refused to ruled out further consultations on eligibility and tariffs in 2016 and will be keeping these under review. For projects waiting in the ‘cap queue’, which are not insulated from future regulatory change, this represents a real risk.
Publikation
The current volatile and unpredictable economic climate creates challenges for businesses.
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2025